What Are the Different Ways to Improve the Procurement Process?
TranquilTRANQUIL

What Are the Different Ways to Improve the Procurement Process?

Home/Blog/What Are the Different Ways to Improve the Procurement Process?
Purchase
February 06, 202610 min read
Share:

Why Procurement Is Worth Fixing First

For most trading, manufacturing and contracting companies, purchases are the largest cost line on the income statement. A distributor turning over SAR 100 million may buy close to SAR 80 million of goods. A factory can spend more than half its revenue on materials and services. That makes procurement the place where a small improvement moves profit the most. Saving 2% on SAR 80 million of spend is SAR 1.6 million straight to the bottom line, a result that would take a large jump in sales to match.

Better procurement is not just squeezing suppliers on price, though. It means buying the right item in the right quantity at the right time, through an approval flow that neither slows the business down nor leaves the door open to abuse, and paying only for what actually arrived at the agreed price. This guide sets out practical ways to improve the procurement process, with worked numbers and tables you can adapt directly.

Start With a Baseline

Before changing anything, pull a few numbers from the last six months. They become the baseline you measure against:

  • Cycle time: days from requisition to purchase order, and from PO to receipt.
  • Off-process spend: supplier invoices that arrived with no PO behind them.
  • Urgent purchases: requests flagged as rush, and how much was paid above normal prices.
  • Suppliers per category: how many vendors supply packaging, spare parts or stationery?
  • Invoice exceptions: how many invoices differed in price or quantity from the PO or receipt?

If those figures take more than a day or two to produce, that is a finding in itself: purchasing data is scattered, and the first improvement is to bring it into one place.

1. Analyze Spend Before You Negotiate

Spend analysis means classifying everything you bought by category, supplier and department, then looking for patterns. A hypothetical mid-sized manufacturer:

CategoryAnnual spend (SAR)SuppliersWhat it suggests
Core raw materials18,000,0004Concentrated; candidate for an annual contract
Packaging2,400,00011Fragmented; consolidate
Spare parts and maintenance1,600,00027Frequent rush buying
Freight1,100,0006Different rates on the same lanes
Office supplies180,0009Low value; simplify rather than negotiate

The table tells you where effort pays. Eleven packaging suppliers means each one sees only a slice of your volume and has little reason to offer its best price. Twenty-seven spare parts vendors usually points to missing planning rather than a negotiation problem, which is covered in section 5.

2. Standardize Specifications and Consolidate Suppliers

Much fragmentation comes from departments ordering slightly different versions of the same thing: three types of gloves, four carton sizes a centimeter apart. Standardizing specs cuts the item count, pools volume and makes supplier comparison straightforward.

Consolidation does not mean single sourcing everything. For critical materials, keep at least one qualified alternate so production does not stop if the main supplier stumbles. A workable rule: a primary supplier takes most of the volume, a secondary gets enough to stay engaged and ready.

3. Build a Clear Approval Matrix

If every request goes to the general manager, purchasing crawls. If approvals are missing, controls disappear. The fix is a matrix that ties approval level to value and purchase type:

Request value (SAR)Quotes requiredApproval
Up to 5,000One quote or approved supplierRequesting department manager
5,001 to 50,000Three quotesDepartment manager and procurement manager
50,001 to 250,000Three quotes plus written comparisonAdd finance manager
Above 250,000Formal RFQ or tenderAdd general manager

The thresholds are illustrative; set your own based on size. What matters is that they are written down and enforced by the system rather than by memory. Watch for split orders: a SAR 60,000 need broken into two SAR 30,000 requests to dodge the higher approval. Repeated requests to the same supplier within a few days are an easy pattern for a system to flag.

4. Automate Procure-to-Pay and Three-Way Matching

The full cycle runs through fixed steps: requisition, approval, PO, receipt, invoice, match, payment. Run on email and paper, documents go missing, nobody knows where a request is stuck, and invoices reach finance late.

How three-way matching works

Before an invoice is approved for payment, the system compares the PO (what we ordered and at what price), the goods receipt (what actually arrived) and the supplier invoice (what we are being charged). A hypothetical case:

LinePOReceiptInvoiceResult
Quantity500 cartons480 cartons500 cartons20 cartons billed but not received
Unit priceSAR 42n/aSAR 44SAR 2 price variance
Amount before VAT21,000n/a22,000Actually due: 480 x 42 = 20,160

Without the match, the company pays SAR 22,000 before VAT instead of SAR 20,160, an overpayment of SAR 1,840 on one invoice. Multiply by hundreds of invoices a month and the value of the control is obvious. A small tolerance, say up to 1% on price, can pass automatically while anything larger goes on hold for review.

E-invoices are part of the match

Under Phase 2 of e-invoicing, standard B2B tax invoices are cleared by ZATCA in real time before they reach the buyer. On receipt, still check the supplier's VAT number and that the invoice is complete, because recovering 15% input VAT depends on a valid tax invoice. An incomplete invoice can mean VAT you cannot reclaim.

5. Cut Rush Buying Through Planning

Rush purchases always cost more: no time to compare, the supplier knows you are stuck, and express freight is expensive. Most of them are not genuine emergencies but the result of missing planning. Three tools help:

  • Reorder points. For regularly consumed items, set a stock level that triggers a requisition. Example: daily usage 40 units, lead time 10 days, safety stock 120 units. Reorder point = 40 x 10 + 120 = 520 units.
  • Requirements planning. Tie purchases to the sales plan, production schedule or project timeline so materials are ordered with enough lead time.
  • Root cause review. Each month, look at rush orders: who raised them, why, and could they have been foreseen? The same departments and reasons tend to repeat.

Our guide to the inventory reorder point covers the calculation in more depth.

6. Score Suppliers on Data, Not Impressions

Price alone misleads. The cheapest supplier who delivers late and ships defects can be the most expensive in practice. A simple weighted scorecard makes comparison objective:

CriterionWeightMeasureSupplier ASupplier B
On-time delivery30%Share of deliveries on the promised date95% (28.5)78% (23.4)
Quality30%100% minus rejection rate98% (29.4)99% (29.7)
Price25%Relative to lowest quote90% (22.5)100% (25)
Responsiveness and documents15%Monthly rating out of 10085 (12.75)70 (10.5)
Total100%93.1588.6

Supplier B is cheaper, but A wins overall on reliability. The scorecard only works if the system records actual receipt dates against PO due dates and rejected quantities at inspection. See our article on supplier performance for more detail.

7. Use Framework Agreements for Repeat Purchases

For items you buy constantly, collecting quotes every time makes little sense. An annual framework agreement fixes prices or a price adjustment mechanism, lead times, quality and payment terms; you then release POs against it as needed. Cycle time drops from days to hours, prices stay stable, and the supplier gets visibility of your volume that helps it plan.

Once the agreement is in the system, the agreed price fills in automatically on the PO, and users get a warning as consumption approaches the ceiling or the agreement nears expiry.

8. Protect Supplier Master Data

Two of the most common procurement frauds are changing a genuine supplier's bank account just before a payment run, and creating a fictitious supplier that bills for services never delivered. A few controls stop most of it:

  • Separate the right to create suppliers from the right to approve payments.
  • Allow bank detail changes only with a second approver and a call-back to a number already on file, never the number in the change request.
  • Review and deactivate dormant suppliers periodically.
  • Run a monthly report of new suppliers and who created them.

9. Check Budget at Commitment, Not at Invoice

Many companies discover a budget overrun when invoices arrive, after the money is already committed. Commitment accounting fixes this: once a PO is approved, its value is reserved against the department or project budget before receipt or invoice.

Hypothetically, a plant's annual maintenance budget is SAR 500,000. By the end of Q3, posted invoices total SAR 260,000, which looks comfortable. But approved POs not yet invoiced add SAR 180,000. The real remaining budget is 500,000 minus 260,000 minus 180,000, or SAR 60,000, not the SAR 240,000 the invoice figure suggests. When the system shows available budget as the request is raised, the maintenance manager knows to prioritize before ordering.

10. Make Requisitioning Easy

A lot of off-process buying happens because the process is painful. If an engineer needs twenty minutes to raise a request for a known part, they will phone the supplier directly. Simple fixes:

  • An approved item catalog with specs, supplier and agreed price for repeat items.
  • Templates for recurring requests such as monthly operating supplies.
  • Visible status, so requesters can see where their request sits and who it is waiting on.

11. Keep Records That Serve Audit and Tax

Every purchase leaves a trail: request, quotes, comparison, PO, receipt, invoice and payment proof. Auditors will ask for it and ZATCA may request tax invoices during a review. Under the VAT Implementing Regulations, records are generally kept for at least six years, eleven years for movable and intangible capital assets, and fifteen years for real estate. When every document links to the PO in the system, pulling a complete file for any purchase takes minutes.

A 90-Day Improvement Plan

DaysWorkExpected result
1 to 30Collect last year's data, run spend analysis, approve the approval matrixClear picture of spend and a ranked list of opportunities
31 to 60Switch on three-way matching; block payment of no-PO invoices except approved exceptionsLess off-process spend and fewer invoice variances
61 to 90Negotiate the first two framework agreements for the most fragmented categories; start scorecards for key suppliersFixed prices on repeat categories and first supplier scores

At day 90, compare your KPIs against the baseline and choose the next phase based on the numbers. For further savings levers, see cost reduction in procurement.

KPIs to Track

KPICalculationBetter when
Requisition-to-PO cycle timeAverage days from request to POLower
Off-process spendNo-PO invoices / all invoicesLower
First-pass match rateInvoices matched without exception / all invoicesHigher
Rush purchase shareValue of urgent orders / total spendLower
Spend under agreementSpend on framework agreements / total spendHigher

A fuller list is in our article on procurement KPIs.

Where an ERP Helps

Most of this is possible on paper or in spreadsheets, but hard to sustain. An ERP links the requisition, PO, receipt and invoice, applies the approval matrix automatically and connects purchasing with inventory and accounting so nobody re-keys data. In Tranquil, purchase management runs in the same cloud system as inventory, sales, financial accounting and ZATCA-compliant e-invoicing, and multi-level approvals, reports and screens can be customized to match your purchasing policy.

Frequently Asked Questions

Where should we start?

With spend analysis. Classify last year's purchases by category and supplier, then start with high-spend, multi-supplier categories, which are usually the fastest source of savings.

What is the difference between two-way and three-way matching?

Two-way compares the PO with the invoice and suits services with no physical receipt. Three-way adds the goods receipt, so you never pay for goods that did not arrive. It is the standard for physical goods.

Does supplier consolidation mean single sourcing?

No. It reduces supplier numbers to pool volume, but critical materials should always have a qualified alternate.

How does e-invoicing affect procurement?

Supplier tax invoices arrive already cleared by ZATCA under Phase 2, but you still need to check their data and match them to the PO and receipt, since input VAT recovery depends on a valid invoice.

Is Tranquil suitable for small companies?

Yes. Small firms can be priced per user; larger ones can choose a flat fee per module with unlimited users. Contact the Tranquil team for a quote within 24 hours.